Jackson Township Will Be Paving 5 Roads This Month

Jackson Township Will Be Paving 5 Roads This Month

JACKSON, NJ – Jackson Township has announced it will continue with a previously approved schedule to re-pave 5 roads in the town.  Here’s the list.

Jackson Township Pavement Improvement
1. Pitney Ln on or about 4/29 to 5/1
a. Milling on Wednesday 4/29
b. Paving 1,536 Tons on Thursday 4/30 & Friday 5/1
2. Nature Blvd on or about 4/29 to 5/4
a. Milling on Wednesday 4/29 & Thursday 4/30
b. Paving 966 Tons on Friday 5/1 & Monday 5/4
3. New Castle Ct & Westminster Dr on or about 4/30 to 5/5
a. Milling on Thursday 4/30 & Friday 5/1
b. Paving on Monday 5/4 & Tuesday 5/5
4. Chelsea Rd & Liverpool Ct on or about 5/4 to 5/7
a. Milling on Monday 5/4 & Tuesday 5/5
b. Paving on Wednesday 5/6 & Thursday 5/7
5. Iris Dr, Steuben Ln, Oak Dr, & Melody Ln on or about 5/6 to 5/11
a. Milling on Wednesday 5/6 & Thursday 5/7
b. Paving on Friday 5/8 & Monday 5/11
Above time frames are contingent upon weather conditions. We will have two crews (one milling & one paving) working on these roads.
Schedule will be revised weekly as any changes are required.